A time study from Lorraine (France)


House erected in Oct. 2002 - one day for setting up the styro stones and concrete pour.

A demonstration for a small house (9*9 m) with trained people


Precut styro stones according to plan.


Range of styro stones to be used.


All the styro stones needed.


Platform.


First layer in place.


Second layer in place.


Trestles in place.


Vertical alignement.


Fourth layer.


Fifth layer, windows openings visible.


Lintels in place.


After 1 hour, first floor is complete.


Front Gables built.


Gables from a different point of view.


Back Gables set, well within the second hour.